Taxiway C between Taxiway N and Taxilane C12 will be closed continuously for construction of the future Taxilane C13 as part of enabling work for the TBIT West South Terminal Project.
This Phase 1 Taxiway C closure between Taxiway N and Taxilane C12 is scheduled April 12, 2022 through July 30, 2022, which will include pavement demolition, construction of new pavement, rerouting of underground utilities, and reconfiguration of taxiway markings, signs and lighting.
The Phase 2 Taxiway C closure between Taxiway L and the future Taxilane C13 (just east of Taxiway N) is scheduled August 07, 2022 through August 28, 2022, which will include construction activities to decommission Taxilane C12 after Taxilane C13 is complete and open for aircraft movement.
Taxiway B13 between Taxiways B and C will be closed continuously during both phases to support the construction activities. |