AI and Contractor RFI Overload
Introduction
Artificial intelligence (AI) is transforming how contractors review construction documents, identify potential discrepancies, and generate Requests for Information (RFIs). While these technologies offer opportunities to improve project coordination and identify design issues earlier, they also introduce a growing risk for architects and engineers (A/E) firms: an overwhelming volume of unnecessary, repetitive, or inadequately reviewed RFIs.
Traditionally, contractors reviewed drawings and specifications, identified specific questions, and submitted RFIs requesting clarification. This process required technical knowledge, document review, and professional judgment. AI has changed that process dramatically. Contractors can now analyze hundreds of pages of drawings and specifications and generate extensive lists of potential discrepancies in minutes. Unfortunately, these questions may be submitted without adequate verification that an actual deficiency exists. A contractor can generate hundreds of RFIs in minutes, while the design team may spend weeks investigating and responding to them.
Beyond an Administrative Burden
Excessive RFIs are not a new problem. Contractors have historically submitted unnecessary questions because of inadequate document reviews, insufficient staffing, poor coordination, or efforts to support additional compensation and schedule extensions. AI can significantly amplify these practices. Automated systems may identify apparent conflicts that are already resolved elsewhere in the documents, generate duplicate questions, or incorrectly interpret design details. Beyond consuming professional resources, excessive RFIs can disrupt schedules, increase costs, and create professional liability exposures.
RFI's and Disputes
Of particular concern is how RFIs may be used in subsequent disputes. A contractor submitting hundreds of RFIs may later argue that the volume demonstrates poorly coordinated or deficient design documents, contributing to project delays and additional construction costs. However, the number of RFIs submitted does not necessarily reflect the quality of the design documents. Without appropriate documentation, design firms may find themselves defending allegations based on misleading RFI statistics.
Contractor Accountability
The objective should not be to discourage legitimate RFIs or the responsible use of AI. Rather, contractors should be required to substantiate questions before submitting them. Design firms should encourage clients to establish clear contractual RFI procedures requiring contractors to:
- Identify the specific deficiency - Each RFI should reference the applicable drawing, sheet, detail, or specification section and clearly describe the information believed to be missing, conflicting, or ambiguous.
- Verify AI-generated questions - A qualified contractor representative should review each RFI, confirm its accuracy, and determine whether the information is already available in the contract documents.
- Eliminate unnecessary submissions - Duplicate questions, requests involving contractor coordination responsibilities, and questions already answered in the documents should be resolved before submission.
- Accept responsibility for RFI accuracy - Using AI should not transfer the contractor’s document review and coordination obligations to the design team.
Example - an RFI requesting clarification of structural connections should identify the particular connection, applicable drawings, and specific information requiring clarification—not simply request a general review of structural details.
Contractual Protection
Design firms should address this exposure before construction begins. Both the Owner–Contractor Agreement and Owner–Design Professional Agreement should establish consistent RFI submission and review requirements. Design professionals should have the contractual authority to return inadequately documented or duplicative RFIs while ensuring legitimate design questions and safety concerns receive timely attention.
Agreements should also provide additional compensation when unnecessary or excessive RFIs create professional service demands beyond the agreed scope, excluding work required to correct the design professional’s own errors or omissions. Importantly, the design firm’s entitlement to authorized additional compensation should not depend on the owner’s ability to recover those costs from the contractor.
Documentation Is Essential
Design firms should track RFIs by category, distinguishing legitimate clarifications, actual design discrepancies, duplicate requests, contractor coordination questions, and information already provided in the documents. This documentation can help identify emerging problems, support discussions with the owner, and provide valuable evidence if disputes develop.
Bottom Line
AI can improve construction coordination, but it should not eliminate contractor accountability.
The fundamental risk management principle is straightforward - Contractors should identify and substantiate the specific alleged deficiency before submitting an RFI. Establishing clear contractual requirements, verification procedures, and documentation practices can help design firms control unnecessary costs, protect project performance, and reduce professional liability exposures. |